12 Lennox Street, Gordon · Construction progress and project evidence

Formwork and services following a Dincel pour

12 Lennox Street, Gordon, NSW 2072, Australia
Reviewed: 1 October 2026 AEST · Stages reflect their dated source records

Recorded workFormwork and services following a Dincel pour
Published site photos8
Original report index3

Project rolesProgressSite photosInspectionsRectification

Project roles and responsibility

The project master reviewed on 30 September 2026 names Sunny Building Construction Pty Ltd in the Builder field. This page presents project coordination, stage records and document management within the AUD operating framework. The master field is a project record; the contract, licence and appointment documents determine construction responsibility.

Projects use their respective responsible entities. The shared management system shows operating coordination; corporate relationships and responsibility are checked against the relevant documents.

Dated construction progress

  1. The report records the Dincel wall concrete pour.

  2. Formwork, site cleaning and reinforcement delivery recorded.

  3. Formwork removal, preparation for reinforcement installation, skip exchange and plumbing pipework recorded.

Photographs from the site

Dates come from the linked PM site record. Photographs show visible work and do not independently certify concealed work or inspection outcomes. Public images have EXIF/GPS metadata removed; originals and hashes are retained in the dossier.

Professional inspection report index

IR02 · 2026-09-04

CDC CK25121/01; ECBCE REF 12626

Exclusive Certifiers Pty Ltd
basment slab / Footings and Slabs · 2 original pages

The basement slab inspection was unsatisfactory and required reinspection; the report raised height, location, set-out and excavation extent matters.

Original identification and review scope

PCA inspection-basment slab-12 Lennox St Gordon.pdf

SHA-256 b9079051c77cfb00316945deaa4ebfcb2c6be4f97897e46fba4b5ca391a04c60

Original-page content reviewed; issuer authenticity and digital signatures were not independently authenticated. This public page provides the source index and summary; complete reports are retained in the dossier.

IR03 · 2026-09-04

SVR25337.02A

QDE Engineering Pty Ltd
Basement slab and footing · 3 original pages

Basement slab and footing requirements included additional horizontal reinforcement and pipe separation material.

Original identification and review scope

SVR25337.02A 12 Lennox st Gordon 04_09_2026.pdf

SHA-256 40cf1a05fd36086e0ffcb0bac702746c8bd9c5c7860e1b6aac9e591ce92649ea

Original-page content reviewed; issuer authenticity and digital signatures were not independently authenticated. This public page provides the source index and summary; complete reports are retained in the dossier.

IR04 · 2026-09-25

SVR25337.03A

QDE Engineering Pty Ltd
Dincel wall · 3 original pages

Dincel wall requirements covered vertical and horizontal reinforcement, extensions and the lift-well area.

Original identification and review scope

SVR25337.03A 12 Lennox St Gordon 25_09_2026.pdf

SHA-256 c96a96cdc1439e8734eff1c7e8fa2cac23cc67bea7d3fb1d8427a74c974ac28c

Original-page content reviewed; issuer authenticity and digital signatures were not independently authenticated. This public page provides the source index and summary; complete reports are retained in the dossier.

QDE reports apply to the specified components and inspection dates, with separate exclusions for ground conditions, formwork/support and specified anchoring, plus clean-out and cover conditions. Each original remains the complete technical reference.

Rectification and stage acceptance records

Management confirmed on 29 September 2026 that rectification and acceptance of completed work stages were complete. The original report requirements are retained. Matching rectification photographs, sign-off dates and professional reinspection/clearance originals still need to be archived item by item. This is not whole-home completion; a different-stage report does not close the earlier finding.

Sources and next steps

This page uses a read-only PM snapshot, the project master/construction task tables reviewed on 30 September 2026, and user-supplied inspection originals whose pages were reviewed. Management records and professional reports are identified separately; photographs were checked for project linkage and visible content.

Next: pair each work stage with its check, before/after rectification photographs and sign-off documents, then add stage-acceptance and whole-home handover records as obtained.

Explore all 11 project dossiers · Public evidence index

Bring your plans into the discussion

Choosing a custom-home or knockdown-rebuild builder? Share the site, drawings, approval status and material specification to discuss roles, work stages, quote inclusions and available site visits.

Discuss your build

Explore custom home construction · Compare builders on the same criteria

PM work schedules and site progress

Read-only extract on 1 October 2026. The table shows stored status, planned dates, actual-finish fields and the last sync date. Some imports predate the site diaries and are historical schedule snapshots. Status and actual-finish fields can differ; blanks remain blank. Planned dates do not establish completed construction or acceptance. Newer master records, professional inspections and signed close-outs are checked separately.

Recent site-record summaries

  1. — Daily records report formwork, plumbing rough-in and preparation of space for reinforcement installation.
Open 16 stored PM schedule records, including older imports
Original task titleStored statusPlanned startPlanned finishActual-finish fieldLast sync
开工Recorded complete2026-05-112026-06-142026-06-142026-07-26
拆房Recorded complete2026-06-142026-07-062026-07-022026-07-26
土方开挖In progress2026-07-102026-08-12—2026-07-26
游泳池施工Recorded complete2026-07-162026-07-272026-07-262026-07-26
OSD和WRT施工Not started2026-07-312026-08-09—2026-07-26
地下室底板浇筑Not started2026-08-062026-08-17—2026-07-26
地下室Dincle墙体浇筑Not started2026-08-182026-08-30—2026-07-26
地下室顶板浇筑Not started2026-08-312026-09-12—2026-07-26
一楼楼板砌砖Not started2026-09-182026-09-27—2026-07-26
二楼楼面模板钢筋浇水泥Not started2026-09-302026-10-17—2026-07-26
Electrical, Plumbing Collar installation, etc. 水电排管-水泥套筒Not started2026-10-112026-10-12—2026-07-26
Top Steel 钢筋施工Not started2026-10-132026-10-15—2026-07-26
Concreting 水泥施工日Not started2026-10-162026-10-17—2026-07-26
二楼木架(水泥强度养护)Not started2026-10-202026-11-02—2026-07-26
二楼砌砖+dincel水泥墙体Not started2026-11-032026-11-09—2026-07-26
屋顶彩钢瓦Not started2026-11-102026-11-29—2026-07-26

Request a site visit and document review — Subject to owner consent, site safety, work in progress and a confirmed time; a request is not a confirmed appointment.