306 Pittwater Road, East Ryde · Construction progress and project evidence
Site coordination and material deliveries
Project rolesProgressSite photosInspectionsRectification
Project roles and responsibility
The AUD operating framework coordinates the project progress and documents shown here. The reviewed project master has no Builder value; the contracting builder is not established in this dossier.
Projects use their respective responsible entities. The shared management system shows operating coordination; corporate relationships and responsibility are checked against the relevant documents.
Dated construction progress
Saw-cutting completion recorded by site personnel.
Site attendance and photographs of materials recorded.
Dincel material delivery recorded.
Site coordination recorded; photographs show fencing, access and the earthworks area.
Photographs from the site








Dates come from the linked PM site record. Photographs show visible work and do not independently certify concealed work or inspection outcomes. Public images have EXIF/GPS metadata removed; originals and hashes are retained in the dossier.
Professional inspection report index
No original professional inspection report for this address is currently in this page’s dossier. Site progress, demolition tasks and scheme meetings are not professional acceptance findings.
Rectification and stage acceptance records
Management has confirmed stage acceptance and related rectification for completed work. This page does not yet have matching professional check/reinspection originals; progress photographs do not establish professional clearance.
Sources and next steps
This page uses a read-only PM snapshot, the project master/construction task tables reviewed on 30 September 2026, and user-supplied inspection originals whose pages were reviewed. Management records and professional reports are identified separately; photographs were checked for project linkage and visible content.
Next: pair each work stage with its check, before/after rectification photographs and sign-off documents, then add stage-acceptance and whole-home handover records as obtained.
Bring your plans into the discussion
Choosing a custom-home or knockdown-rebuild builder? Share the site, drawings, approval status and material specification to discuss roles, work stages, quote inclusions and available site visits.
Discuss your buildExplore custom home construction · Compare builders on the same criteria
PM work schedules and site progress
Read-only extract on 1 October 2026. The table shows stored status, planned dates, actual-finish fields and the last sync date. Some imports predate the site diaries and are historical schedule snapshots. Status and actual-finish fields can differ; blanks remain blank. Planned dates do not establish completed construction or acceptance. Newer master records, professional inspections and signed close-outs are checked separately.
Recent site-record summaries
- — The daily record reports an on-site meeting/coordination, without a new quantity or acceptance finding.
- — The daily record reports delivery of Dincel materials.
Open 5 stored PM schedule records, including older imports
| Original task title | Stored status | Planned start | Planned finish | Actual-finish field | Last sync |
|---|---|---|---|---|---|
| 拆房 | Recorded complete after planned date | 2026-02-08 | 2026-05-19 | 2026-06-17 | 2026-07-26 |
| 路基(含雨水) | Not started | 2026-07-27 | 2026-08-06 | — | 2026-07-26 |
| 路面垫层 | Not started | 2026-08-07 | 2026-08-12 | — | 2026-07-26 |
| 路面面层 | Not started | 2026-08-13 | 2026-08-18 | — | 2026-07-26 |
| 雨水施工、验收 | Not started | 2026-08-19 | 2026-08-26 | — | 2026-07-26 |
Request a site visit and document review — Subject to owner consent, site safety, work in progress and a confirmed time; a request is not a confirmed appointment.