Sydney residential projects · Dated site records
51 Lamorna Avenue, Beecroft · Construction progress and project evidence
Road and stormwater coordination following demolition
Project rolesProgressSite photosInspectionsRectification
Project roles and responsibility
The AUD operating framework coordinates the project progress and documents shown here. The reviewed project master has no Builder value; the contracting builder is not established in this dossier.
Projects use their respective responsible entities. The shared management system shows operating coordination; corporate relationships and responsibility are checked against the relevant documents.
Dated construction progress
The construction task table records demolition complete on 11 May.
The task table records the stormwater-pit scheme coordination complete and a meeting on this date.
The table reviewed on this date still lists road and stormwater works as outstanding. Notes describe road finishing after stormwater work and drainage work dependent on Council approval. Current field completion needs dated photographs and sign-off.
Photographs from the site
Professional inspection report index
No original professional inspection report for this address is currently in this page’s dossier. Site progress, demolition tasks and scheme meetings are not professional acceptance findings.
Rectification and stage acceptance records
Professional checks, specific rectification requirements and reinspection originals have not yet been paired for this project. Road and stormwater tasks are coordination items; they do not establish rectification closure or whole-home acceptance.
Sources and next steps
This page uses a read-only PM snapshot, the project master/construction task tables reviewed on 30 September 2026, and user-supplied inspection originals whose pages were reviewed. Management records and professional reports are identified separately; photographs were checked for project linkage and visible content.
Next: pair each work stage with its check, before/after rectification photographs and sign-off documents, then add stage-acceptance and whole-home handover records as obtained.
Bring your plans into the discussion
Choosing a custom-home or knockdown-rebuild builder? Share the site, drawings, approval status and material specification to discuss roles, work stages, quote inclusions and available site visits.
Discuss your buildExplore custom home construction · Knockdown rebuild scope and process · Compare builders on the same criteria
PM work schedules and site progress
Read-only extract on 1 October 2026. The table shows stored status, planned dates, actual-finish fields and the last sync date. Some imports predate the site diaries and are historical schedule snapshots. Status and actual-finish fields can differ; blanks remain blank. Planned dates do not establish completed construction or acceptance. Newer master records, professional inspections and signed close-outs are checked separately.
Recent site-record summaries
No daily-progress photo record linked to this address was found in this PM read. The page retains the newer 30 September master-table review; the July PM import does not override that review.
Open 4 stored PM schedule records, including older imports
| Original task title | Stored status | Planned start | Planned finish | Actual-finish field | Last sync |
|---|---|---|---|---|---|
| 拆房 | Recorded complete after planned date | 2026-04-12 | 2026-04-24 | 2026-05-10 | 2026-07-26 |
| 道路施工 | In progress | 2026-06-04 | 2026-08-19 | — | 2026-07-26 |
| 雨水施工、验收 | In progress | 2026-06-14 | 2026-08-14 | — | 2026-07-26 |
| 雨水积水坑方案确认(约coucel会议),自然排入公园 | In progress | 2026-07-23 | 2026-07-30 | — | 2026-07-26 |
Request a site visit and document review — Subject to owner consent, site safety, work in progress and a confirmed time; a request is not a confirmed appointment.